Construction Progress

WORKS PROGRESS REPORT HIMALAI PROJECT FOR JUNE, 2019

Works to the structures and clearing the main area for the road are proceeding well due to the good weather. We have not lost too much time to the rains -- we have been fortunate most of the rain has fallen at night or early morning.

The structures for N2 and N3 are completed. Now we are planning and working on the next phase, doing the 1st fix MEP works for the water pipes, electric conduits and waste water management. All these works need to be combined so we don't get obstructions. We’re following the architect’s drawings and combining together the structural and architectural drawings which is leading to the whole project coming together.

E1 building is coming on well and is quickly rising behind the other buildings. E2 and E8 are coming up with N1, and we will announce the next 3 blocks shortly as we now have 3 tower cranes in operation on this project.

We are now working on the infrastructure and have once again we hit rock. This has to be removed -- at least we can say it's a very solid site.

In addition to these works we have been placing the waste water treatment tanks into position. The EIA are very strict about this. We also understand and support the importance of being ECO friendly.

Our teams of designers, consultants, engineers, main contractors and sub contactors meet weekly to discuss project progress and plan outstanding goals and project milestones. We work closely together carefully going through a step by step process to ensure that the project will be a great success -- it will be.

WORKS PROGRESS REPORT HIMALAI PROJECT FOR May 24, 2019

(Above) Building C1 swimming pool formwork.

Building C1 – Swimming pool gutter is finished. Swimming pool concrete wall on-going.

Building C2 – The 1st level of tie beams is finished. Formwork removed. Columns for next floor started.

Building C3 – Column work has been added on top of the footing.

(Above) Building C2 with another floor of column work.

(Above-left) Overall area of building C1-C3. (Above-right) More of the footing work for Building C3.

WORKS PROGRESS REPORT HIMALAI PROJECT FOR MAY 16, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR MAY 02, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR APRIL 25, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR NOVEMBER 2018

WORKS PROGRESS REPORT HIMALAI PROJECT FOR DECEMBER 2017

WORKS PROGRESS REPORT HIMALAI PROJECT FOR APRIL 2017

WORKS PROGRESS REPORT HIMALAI PROJECT FOR OCTOBER 2016

WORKS PROGRESS REPORT HIMALAI PROJECT FOR SEPTEMBER 2016

WORKS PROGRESS REPORT HIMALAI PROJECT AUGUST 2016