Construction Progress

WORKS PROGRESS REPORT HIMALAI PROJECT FOR June, 2019

Works to the structures and clearing the mainarea for the road are proceeding and due to the good weather in which we have not lost to much time from the rains we have been fortunate as most of the raining hasbeen at night or early morning.

The structures are doing well to N2 and N3 which are completed and now we are planning and working on the next phase of doing the 1st fix MEP works for the water pipes, electric conduits and waste water management all these works need to be combined so we don't get obstructions so we follow the architects drawings and combine together with the structural and architectural drawings which leads to the whole project coming together.

E1 buildingis coming on well and is quickly arising behind the other buildings and then we have E2and E8coming up with N1and we will announce the next 3 blocks shortly as we have 3 tower cranes now operation on the project.

We are now working on the infrastructure and have once again we hit so rock and this has to be removed at least we can say it's a very solid site.

In addition to these works we have been placing the waste water treatment tanks into position as the EIA are very strict about this and we also feel the importance of being ECO friendly.

Are teams of designers, consultants, engineers, main contractors and sub contactors meet weekly to discuss the progress of the project also all the future planningand work closely together careful going through a step by step process to ensure that the project will be a great success and it will be.

WORKS PROGRESS REPORT HIMALAI PROJECT FOR May 24, 2019

(Above) Building C1 swimming pool formwork.

Building C1 – Swimming pool gutter is finished. Swimming pool concrete wall on-going.

Building C2 – the 1st level of tie beams is finished. Formwork removed. Columns for next floor started.

Building C3 – Column work has been added on top of the footing.

(Above) Building C2 with another floor of column work.

(Above-left) Overall area of building C1-C3. (Above-right) More of the footing work for Building C3.

WORKS PROGRESS REPORT HIMALAI PROJECT FOR May 16, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR May 02, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR April 25, 2019

WORKS PROGRESS REPORT HIMALAI PROJECT FOR NOVEMBER 2018

WORKS PROGRESS REPORT HIMALAI PROJECT FOR DECEMBER 2017

WORKS PROGRESS REPORT HIMALAI PROJECT FOR APRIL 2017

WORKS PROGRESS REPORT HIMALAI PROJECT FOR OCTOBER 2016

Works Progress Report Himalai Project for September 2016

Works Progress Report Himalai Project August 2016